PIP ELTFT01
Field Inspection and Testing of March 2001
New Electrical Equipment
Process Industry Practices Page 4 of 23
IEEE 576-2000 - Recommended Practice Installation, Termination, and
Testing of Insulated Power Cable as Used in the Petroleum and Chemical
Industry
International Electrical Testing Association (NETA)
NETA ATS-1999 - Acceptance Testing Specifications for Electrical Power
Distribution Equipment and Systems (NETA ATS)
3. Definitions
Check: Inspection to verify conformance with drawings and specifications; does not require
witnessing by Owner’s authorized representative.
CPT: Control power transformer
CT: Current transformer
Function test: A complete operational check of the entire system; requires witnessing by
authorized representative unless waived in writing.
Inspect: A detailed physical inspection of equipment to verify conformance to drawings and
specifications; requires witnessing by Owner’s authorized representative unless waived in
writing
MCC: Motor control center
PT: Potential transformer
Test: Application of external power source or test equipment to prove the integrity of the unit
or system; requires witnessing by Owner’s authorized representative unless waived in
writing.
Tester: The party responsible for conducting the check items, inspection items, testing
requirements, and function test items as covered herein for installed electrical equipment and
electrical facilities as defined in the project scope
4. General
4.1 The Tester shall comply with all federal, state, and local regulations and codes as
well as with site-specific safety procedures and requirements.
4.2 Before beginning any inspection and testing, the Owner and the Tester must agree on
the electrical inspection and testing procedures.
4.3 Tester shall confirm that all check items, inspection items, and testing are performed
before placing any equipment in operation.
4.4 The Tester shall be responsible for arranging and conducting the testing per the
approved project schedule.
Page view 148