01001-1
07/26/10
L:\wpb_\wpb_emp1\W1200.13\p.m. Project #1\01001-072610 Noboil.doc
Engineer’s Proj. PROJECT: East Central Regional Water Reclamation Facility
No. W1200.13 Emergency Power Plant Upgrades
Electrical Systems and Structural Project
SECTION 01001
GENERAL REQUIREMENTS
1.0 PROJECT LOCATION
The East Central Regional Water Reclamation Facility located in West Palm Beach, Florida in
Township 43 South, Range 42 East, Section 11. The street address is 4325 N. Haverhill Road, West
Palm Beach, Florida. See construction drawings (Mock•Roos Dwg. No. 43-42-11-35) for specific
location of the Emergency Power Plant.
2.0 SCOPE OF WORK
A. The Work to be performed by the Contractor includes permitting, inspections, furnishing all
materials, labor, tools, equipment, water, light, power, transportation, superintendence,
temporary construction of every nature, and all other services and facilities of every nature
whatsoever necessary to modify, construct, complete, deliver and place in operation the above
referenced Project as shown on the Drawings and/or as herein described as specified. All Work
to be in accordance with the Contract Documents.
3.0 REFERENCE POINTS
A. Not Used.
4.0 GRADES, DIMENSIONS, AND ELEVATIONS
A. Written dimensions have preference over scaled dimensions.
5.0 EXISTING STRUCTURES AND UTILITIES
A. All known utilities have been shown on the Drawings according to the best information
available. It is the Contractor's responsibility to contact all owners of structures or utilities above
ground, on the surface, or below the ground, within the Project area so that said owners may
stake or otherwise mark or protect their facilities. The Contractor must provide facilities and be
responsible for the protection of all structures, buildings and utilities, underground, on the
surface, or above ground against trenching, dewatering, or any other activity connected with the
Work throughout the entire Contract Time.
B. When structures and utilities have been properly shown or marked and are disturbed or damaged
in the execution of the Work, they must be repaired immediately in conformance with best
standard practice and the approval of the owner of the damaged utility or structure. In the case of
structures and utilities which have not been properly shown or located as outlined above and are
disturbed or damaged in the prosecution of the Work, take whatever steps are necessary for
safety and notify the affected utility owner and avoid any actions which might cause further
damage to the structure or utility.
C. Should the Work require repairs, changes or modifications of the Owner's utilities as well as
other utilities, it is the responsibility of the Contractor to provide for the maintenance of
continuous water, sewage, electric, telephone and other utility services to all present customers
of such utilities, unless approval in writing is secured from the applicable utility company or
Owner for interruption of such service.